    Chandler opened its new City Hall facility in October of 2010.Chandler_City_Hall_Nov2010-a.jpg

     

    Key Project Dates:
      
    * Chandler City Hall Site 
       Selection Study Approved:
          May 2006
    * Design Contract Approved:
          Dec. 13, 2007
    * Construction Contract
       Approved:
          April 6, 2009
    * Groundbreaking Ceremony: 
          May 8, 2009
    * Public Opening: 
          Oct. 25, 2010
    * Dedication Ceremony: 
          Nov. 15, 2010

    Key Budget Figures:
      
    * Original Project Budget
          $80 million (see below)
    * Original Construction
          Estimate: $51 million
    * Guaranteed Maximum Price
       Construction Bid:
          $47 million (Sundt Const.)
    * Additional Savings Realized
       During the Project:
          $6 million
    Final Project Cost Estimate:
          $70 million

     

     

    To see photos of the building, CLICK HERE.

    To take a video tour of the building, CLICK HERE.

    Tag page (Edit tags)
    • No tags
    Page statistics
    3054 view(s), 3 edit(s) and 2175 character(s)

    Comments

    You must login to post a comment.

    Attach file

    Attachments

    FileSizeDateAttached by 
     Chandler_City_Hall_Nov2010-a.jpg
    No description
    37.07 kB09:10, 10 May 2013natemActions